CES Building Project update: (09/15/15)
We have the final plans approved. Bidding for the project will close on 9/29/15. 2:00pm.
8 construction companies were in attendance at the pre-bid meeting.
LCS Board meeting will be on Oct 6th to accept the lowest bid.
**********************
Base Bid estimated @ $5,875,900
22 classroom addition + gym
Alternates estimated @ 1,037,000
A1 - $250,000 - gym rear parking and access road from Sanderson to back of gym in between soccer and baseball fields
A2 - $175,000 - Lunchroom addition
A3 - $200,000 - 30 parking spaces and redesign of the front parking lot
A4 - $206,000 - 2 Classroom addition
A5 - $206,000 - 2 Classroom addition
Total = $6,912,900
3 versions of a storm shelter are being reviewed and it will be decided upon the final amount left in the budget after the base bid and the alternates have all come in.
- Traditional
- Remagen
- Modular
Estimated value of shelter = $1,750,000 - $2,000,000
New Building Plan
The new school building will be for grades 3, 4 and 5 and will be connected to the original building on the south side of campus.
22 to 26 regular classrooms & Music Room for grades K-5 to share.
Front office for new school is in orange with parking in front of the new school.
The plan is for the new school to have it's own front office staff.
Gymnasium for the new school is in yellow.
The gym for the new school will be slightly bigger than Creekside's current gym. The playing floor will be wider and longer w/ no stage.
View is front of Creekside with possible front parking lot addition. The original Creekside will become grades K, 1st and 2nd.